Secant pile — Kota Baru Parahyangan

Tatar Surawisesa

A secant pile retaining wall across two areas of the Tatar Surawisesa cluster at Kota Baru Parahyangan. 338 bored piles in total, built in two stages over five months.

Area 2 covers 175 piles: 87 primary piles at Ø 600 mm and 88 secondary piles at Ø 800 mm, the secondary piles spaced 1,200 mm centre to centre with an effective length of 20.10 m. The Club House area covers 163 piles at Ø 500 mm — 81 primary and 82 secondary — spaced 900 mm, effective length 15.10 m.

Primary piles use fc’ 12.5 MPa concrete and are bored first; secondary piles at fc’ 30 MPa are then cut into them. Measured overlap is 100 mm in Area 2 and 50 mm at the Club House, giving a continuous wall with no gaps. Every pile position was re-surveyed after boring and recorded in its own piling record.

Secant pile boring at Tatar Surawisesa, Kota Baru Parahyangan
Fig. 01 — Secant pileKota Baru Parahyangan
Secant pile
338 piles
Diameter
Ø 500–800 mm
Effective length
15.1 & 20.1 m
Concrete grade
fc’ 12.5 & 30 MPa
Concrete volume
2,267 m³
Period
Sep 2025–Jan 2026

On site

October 2025
Crawler crane and rotary rig at the Tatar Surawisesa site
Fig. 02 — Rotary rig & craneOctober 2025

Other Projects

Field track record

Discuss your requirements

Not sure which foundation method suits your site? Just describe the conditions — our engineering team is glad to help, with no obligation.

WhatsApp: +62 811-902-590
Office
Ruko Asia Tropis blok AT12 no. 21, Kota Harapan Indah, Bekasi Regency, Indonesia
Opening Hours
Monday–Friday 10:00–17:00
Saturday 10:00–12:00
Closed on Sundays and public holidays
Phone / WhatsApp
+62 811-902-590