Soldier piling — Serpong, South Tangerang

Indah Kiat Pulp & Paper

An earth retaining wall within the Indah Kiat Pulp & Paper Tangerang Mill, Serpong. We built over 200 soldier piles Ø 600 mm with a 7 metre effective length, following a long alignment past warehouses, a pump room, a water pit and pipe racks — all of which stayed in operation.

Drilling used the dry boring method with full casing — steel casing holding the bore wall over the full depth, chosen because the ground here could not be relied on to stand unsupported during drilling and concreting. Reinforcement was graded to the moment profile: dense at the head, opening out towards the toe.

Alongside the soldier piles we carried out Ø 500 mm pre-boring to 9 metres to assist driving at certain points. Pile capacity was verified through three PDA test points spread along the wall alignment.

Indah Kiat Pulp & Paper Tangerang Mill — Serpong
Fig. 01 — Soldier pilingSerpong
Soldier piling
200+ piles
Diameter
Ø 600 mm
Effective length
7 m
Drilling method
Dry boring
Bore support
Full casing
Steel grade
BJTS-42

Other Projects

Field track record

Discuss your requirements

Not sure which foundation method suits your site? Just describe the conditions — our engineering team is glad to help, with no obligation.

WhatsApp: +62 811-902-590
Office
Ruko Asia Tropis blok AT12 no. 21, Kota Harapan Indah, Bekasi Regency, Indonesia
Opening Hours
Monday–Friday 10:00–17:00
Saturday 10:00–12:00
Closed on Sundays and public holidays
Phone / WhatsApp
+62 811-902-590