Services — Continuous Retaining Wall

Secant Pile Contractor

A secant pile wall is a continuous earth retaining structure formed from interlocking bored piles, leaving no gap. It is chosen when the wall must hold back water, or when the soil between piles cannot be relied on to stand alone — conditions common in deep excavation and slope works.

Where the groundwater table is low and the soil cohesive enough, spaced soldier piling is usually more economical. Secant piling is chosen precisely when conditions rule that option out.

Earth retaining wall works on site
Fig. 01 — Retaining wallOn site
Diameter
Ø 500 mm
Ties
D13-150 spiral
Concrete grade
fc’ 30 MPa
Cover
75 mm
Reinforcement
17 D25

How It Works

Primary & secondary
01
Primary piles

Alternate piles are built first as primaries, setting out the spacing along the wall alignment.

02
Secondary piles

The piles between them are bored afterwards, cutting into the primaries on either side — this is where the gap closes.

03
Capping beam

All pile heads are tied by a capping beam that makes the row act as a single wall rather than separate piles.

04
Sequence matters

The interval between primary and secondary must be right: too soon and the primary concrete is not yet strong enough; too late and cutting into it becomes difficult.

Case Study: Kota Baru Parahyangan

Bandung — 2025

An earth retaining wall running 73.5 metres within the Kota Baru Parahyangan development, Bandung. Ø 500 mm piles use 17 D25 reinforcement with D13-150 spiral ties and fc’ 30 MPa concrete, tied by a 100×75 cm capping beam along the alignment.

The wall sits on the property boundary directly alongside the road reserve, with fill on one side and cut on the other — so the retained height differs between the two faces. Concrete cover for the secant piles is set at 75 mm, thicker than for ordinary piles.

Wall length 73.5 m Capping beam 100×75 cm Shop drawing 2025

Service Area

Greater Jakarta and beyond Java

We are based in Bekasi Regency and work from Greater Jakarta through to islands beyond Java. A secant pile wall is chosen when water has to be held back as well as soil — on deep excavations with a high water table, or on slopes that cannot afford to lose groundwater because of what stands above them.

Jakarta Bekasi & Serpong Banten Bandung & Kota Baru Parahyangan Semarang Manado

How We Work Together

From soil data to completed excavation
01
Data

A boring log with groundwater levels, the planned excavation depth, a site layout, and the position of surrounding buildings. For a cut-off wall, the water data matters most.

02
Wall geometry

Primary and secondary pile diameters, centre-to-centre spacing and the overlap are calculated first. Too little overlap leaks; too much makes the work far slower.

03
Quotation

The scope is stated openly: number of primary and secondary piles, the concrete grade for each, capping beam, and testing.

04
Sequenced construction

Primary piles are cast first, then secondary piles are drilled so that they cut into both neighbours. The sequence and the interval between them decide how cleanly the cut is made — primary concrete must not be too hard by then.

05
Staged excavation & monitoring

Excavation layer by layer, with wall movement and settlement of nearby buildings monitored where relevant.

What You Receive

Geometry that can be checked

In a cut-off wall it is not only the quality of each pile that matters but the accuracy of its position. As-built coordinates are therefore surveyed and checked against the design — on the Tatar Surawisesa project the overlap between piles was verified from surveyed X/Y coordinates rather than assumed from the drawing.

Piling record per pile As-built coordinates & overlap Daily reports Photos per stage PIT / PDA results

Questions and Answers

The ones we are asked most

When is a secant wall better than soldier piles?

When water has to be held back. A soldier pile wall has gaps and lets groundwater through; secant piles cut into each other and retain soil and water together.

Is dewatering still needed?

Usually much less of it, because only the water inside the excavation has to be pumped rather than the surrounding groundwater. That is also why secant walls are chosen near existing buildings: pumping large volumes of groundwater risks settling the ground around the site.

What are primary and secondary piles?

Primary piles are cast first, normally in a weaker mix so that they can be cut. Secondary piles are drilled between them, cutting into both, and these are the reinforced, load-carrying piles.

How much overlap is needed between piles?

It comes from the design geometry and is verified on site. At Tatar Surawisesa, overlaps of 100 mm and 50 mm were achieved across every pair of piles, proven from surveyed coordinates.

Is the wall genuinely water-tight?

Water-tight in practical terms: seepage is small enough to handle with light pumping inside the excavation. Leaks usually come not from the method but from insufficient overlap or piles drifting off line.

How does the programme compare with soldier piles?

It is longer, because there are more piles per metre of wall and the sequence is tighter. That extra time is repaid if the alternative is pumping groundwater continuously throughout the substructure works.

Discuss your requirements

Not sure which foundation method suits your site? Just describe the conditions — our engineering team is glad to help, with no obligation.

WhatsApp: +62 811-902-590 Download Company Profile PDF · 3 MB
Office
Ruko Asia Tropis blok AT12 no. 21, Kota Harapan Indah, Bekasi Regency, Indonesia
View on Google Maps →
Opening Hours
Monday–Friday 10:00–17:00 WIB (UTC+7)
Saturday 10:00–12:00 WIB
Closed on Sundays and public holidays
Office Phone
+62 21 8889 8292
WhatsApp / Mobile
+62 811-902-590