Services — Groundwater Control

Dewatering Services

Dewatering is the work of lowering the groundwater table during construction so the excavation stays dry and stable. Without it, water enters the excavation, the base softens, and the substructure works below cannot be executed properly.

This is not standalone work. Dewatering almost always runs alongside earth retention — the wall holds the soil, dewatering holds the water. The two must be planned together, not in sequence.

Excavation flooded before groundwater control
Fig. 01 — High water table in the excavationAIS Tunnel, Jakarta
Target water level
1–1.5 m below excavation base
Method
Deep wells & sump pit

How It Works

Lower it, then hold it
01
Deep wells

Deep wellss are bored around the excavation and fitted with submersible pumps. These wells lower the water table across the whole area, rather than merely removing water that has already entered.

02
Gradual drawdown

The water level is drawn down in stages until it sits below the excavation base — not all at once, so the surrounding ground does not settle abruptly.

03
Sump pit & surface pumps

Water that still seeps into the excavation collects in a sump pit and is pumped out. This complements the deep wells; it does not replace them.

04
Maintained to completion

Pumps run continuously through the substructure works. Stop too early and the water rises again before the structure is strong enough to resist it.

Applied Example

AIS Tunnel, Jakarta

On the Australian Independent School tunnel works, the groundwater table sat at elevation +7.500 while the excavation base lay well below it. The method statement called for drawing the water down to around +1.000 to +1.500 — one to one and a half metres below the excavation base.

Two deep wells with submersible pumps were installed for this, together with two to four surface pumps and a sump pit keeping the water from rising again while excavation and structural works proceeded.

2 deep wells Submersible pumps Sump pit & surface pumps

Discuss your requirements

Not sure which foundation method suits your site? Just describe the conditions — our engineering team is glad to help, with no obligation.

WhatsApp: +62 811-902-590
Office
Ruko Asia Tropis blok AT12 no. 21, Kota Harapan Indah, Bekasi Regency, Indonesia
Opening Hours
Monday–Friday 10:00–17:00
Saturday 10:00–12:00
Closed on Sundays and public holidays
Phone / WhatsApp
+62 811-902-590